We would like to keep parishioners informed about ongoing projects and Stewardship in Action and will use space in the bulletin and on our web site to do that:
Project | Status |
New Grand Entrance to Immaculate Conception: Expansion of Entrance Lanes | Awaiting DOT Permit 09.09.24 |
Repair the Cracked Parapet of Fr. Fata Hall | In Process |
Point the External Northwest Walls of Immaculate Conception Regional School | In Process |
Parging and Repair the Wall facing Pleasant Avenue | Developing Designs |
Air Conditioning of Fr. Fata Hall | Developing Designs |
Clear and Reconstruct the IC Convent to build the St. Frances Cabrini Apartments for Persons with Autism | Nearing Completion |
Repair and Restore the Chimney Above Fr. Fata Hall | Completed 11.18.24 |
Restore and Upgrade the Prayer Garden of Assumption Church | Completed 10.6.24 |
Replace the Stone Staircase for the Parking Lot Entrance of Immaculate Conception Church | Completed 10.1.24 |
Reseal and Resurface the Asphalt of the Upper Parking Lot of Assumption Church and by the Immaculate Conception Rectory Garages | Completed 08.24.24 |
Black Memorial Bricks in the Prayer Garden of Assumption Church | Completed 08.15.24 |
Install New Stonework for the Portico at Assumption Church | Completed 07.28.24 |
Create the Shrine of Our Lady of Guadalupe at Assumption Church | Completed 07.21.24 |
Repave the Hill Between Immaculate Conception Church and Rectory | Completed 07.18.24 |
Two Trees of Life (One in Immaculate Conception Church and One in Assumption Church) | Completed 06.27.24 |
Install Proper Lighting for the Upper Parking Lot of Assumption Church | Completed 06.10.24 |
Install New Stove and Refrigerator in Fr. Fata Hall | Completed 06.08.24 |
Repair Bells and Bell Tower Structure at Assumption Church | Completed 05.24.24 |
Restore the Shrine and Statue of Our Lady, Queen of Heaven on Route 22 | Completed 05.21.24 |
Repair the Retaining Wall on the Hill Between Immaculate Conception Church and Rectory | Completed 04.16.24 |
Install New Doors for the Parking Lot Entrances of Immaculate Conception Church | Completed 04.16.24 |
Repair the Roof of Casa Padre Pio | Completed 04.16.24 |
Repair the 5 Roofs of Immaculate Conception Regional School | Completed 04.10.24 |
Replace the Condenser for the Boiler of Immaculate Conception Regional School | Completed 11.11.23 |
Replace Gutters of Immaculate Conception Church | Completed 09.18.23 |
Install Wrought Iron Handrails to the Church Doors on Winter Hill Road at Immaculate Conception Church | Completed 03.04.23 |
Install New Flooring and Appliances in the Kitchen of the Immaculate Conception Rectory | Completed 02.09.23 |
Purchase of a 2017 GMC HD Truck with V-Plow and Bed Salter (Certified Used) | Completed 12.20.22 |
Demolition of 253 White Plains Road | Completed 11.18.22 |
Install 10 New Protective Glass Coverings over the Stained Glass Windows of Immaculate Conception Church | Completed 11.11.22 |
Reseal and Resurface the Asphalt of Holy Mount Cemetery and the Parking Lots of the Assumption Church | Completed 08.07.22 |
Repair the Wrought Iron Handrails and the Handicapped Accessible Walkway to the Lower Church at Immaculate Conception | Completed 06.23.22 |
Install Two Large St. Killian Votive Candle Racks in the Narthex of Immaculate Conception Church | Completed 02.15.22 |
Columbarium at Holy Mount Cemetery | Completed 01.17.22 |
Install New Flooring for the Narthex of Immaculate Conception Church | Completed 12.31.21 |
Install New Flooring for the Choir Loft and the Stairs Leading to the Choir Loft of Immaculate Conception Church | Completed 12.22.21 |
Install Security System for: Immaculate Conception Church (Upper and Lower), Parish Center and Gym, and Assumption Church and Fr. Fata Hall | Completed 10.08.21 |
Replace the Handrails Leading to the Cafeteria of Immaculate Conception Regional School | Completed 09.17.21 |
Repair the Wrought Iron Handrails for the Handicapped Accessible Ramp to Fr. Fata Hall | Completed 09.16.21 |
Renovation of 65 Winter Hill Road | Completed 07.09.21 |
Install Wi-Fi in Fr. Fata Hall | Completed 05.05.21 |
Renovation of the Kitchen of the Lower Church at Immaculate Conception | Completed 05.04.21 |
Landscape the Grounds of the Garden of Our Lady of the Immaculate Conception Outside the Sacristy of ICC | Completed 05.01.21 |
Install New Lighting in the Crucifixion Scene and the Shrine to Our Lady on Route 22 | Completed 04.22.21 |
Receive Certificate of Compliance for the New Parish Center at Immaculate Conception | Completed 03.22.21 |
Add Dropped Ceiling and Lighting, Repaint the Interior, and Modify the Sound System of the Lower Church at Immaculate Conception | Completed 03.02.21 |
New Floor for the Sacristy of Immaculate Conception Church | Completed 02.22.21 |
Repair Turbines for Heat in the Parish Gymnasium | Completed 02.21.21 |
New Condensation Pumps for Immaculate Conception Regional School | Completed 01.15.21 |
New HVAC in Casa Padre Pio | Completed 01.04.21 |
New Parish Center at Immaculate Conception | Completed 10.15.20 |
Renovation of the Six Rooms in Lower Fr. Fata Hall | Completed 10.15.20 |
Install Shrine to Blessed Clelia Merloni | Completed 10.14.20 |
Restore the Outdoor Statue of St. Rocco at Assumption | Completed 10.09.20 |
Restore the Outdoor Shrine to St. Rocco at Assumption | Completed 10.09.20 |
Install New Signage at Immaculate Conception (Of Note: 2 Wood-Carved Signs Located at the Corner of White Plains Road and Winter Hill Road & at the Pathway to the New Parish Center) | Completed 08.10.20 |
Divine Mercy Chapel in New Parish Center | Completed 08.05.20 |
Install Statue of St. Francis and Landscape the Grounds of the Garden of St. Francis | Completed 08.01.20 |
Construction of New Handicapped Parking at Immaculate Conception | Completed 07.09.20 |
Extension of the Pavers and Gardens by the Statue of Our Lady Outside the Sacristy of ICC | Completed 07.09.20 |
Restoration of the Sacred Heart Statue Near the Entrance of the Assumption Church Parking Lot | Completed 07.03.20 |
Install New Lighting in the Shrines to Our Lady of the Annunciation and to St. Joseph in ICC | Completed 07.02.20 |
Restore, Repair, Paint, and Add Signs to the Shrine to Our Lady on Route 22 | Completed 06.10.20 |
Painting Exterior of 65 Winter Hill Road | Completed 06.03.20 |
Landscaping around the Rectory Grounds | Completed 05.30.20 |
Replace and Automate the Maintenance Garage Door | Completed 05.29.20 |
Repair the Gates on Dempsey Place | Completed 05.27.20 |
Restore the Statues of the Crèche of Assumption Church | Completed 01.15.20 |
Install New HVAC in Immaculate Conception Church | Completed 01.13.20 |
Install New Lighting Board in Immaculate Conception Church | Completed 01.12.20 |
Place Statue of Our Lady of the Immaculate Conception in Garden Outside the Sacristy of ICC | Completed 01.02.20 |
Repair Infrastructure of the Bell Tower of Immaculate Conception Church | Completed 12.31.19 |
Repair and Repaint the Exterior Sashes of the Stained Glass Windows of Assumption Church | Completed 12.22.19 |
Install Wrought Iron Railings for Handicapped Accessible Entrance to New Parish Center | Completed 11.09.19 |
Handicapped Accessible Entrance to New Parish Center, Lower Church, Rear of School, and Convent | Completed 09.21.19 |
Install New Lighting on the Façade of Immaculate Conception Church | Completed 09.19.19 |
Installation of New Kitchen in 61 Winter Hill Road (Formerly known as the Meeting House) | Completed 08.22.19 |
Repoint the Steps in the Front of Immaculate Conception Church | Completed 07.25.19 |
Install New Air Conditioning Units in Casa Padre Pio | Completed 07.03.19 |
Replace Windows of Casa Padre Pio | Completed 07.02.19 |
Vinyl Floor Covering and Rack for the Parish Gymnasium | Completed 05.03.19 |
Restoration of Assumption Church | Completed 04.17.19 |
Repair and Restorative Painting of the Statuary at Assumption Church | Completed 02.15.19 |
Install New Boiler System and Hot Water Heater for Fr. Fata Hall | Completed 02.07.19 |
Repair and Replace the Protective Windows of the Stained Glass Windows in Immaculate Conception Church as well as the Broken Windows in the Lower Church | Completed 02.07.19 |
Transfer (from St. Joseph's Church on Monroe Street in NYC), Clean, and Place 4 Marble Statues in Immaculate Conception Church | Completed 01.25.19 |
Restoration of the First Station of the Cross at Immaculate Conception Church | Completed 01.04.19 |
5 Oak Frontals and Kneelers for the Front Pew Installed in Immaculate Conception Church | Completed 11.09.18 |
Motorized All Four Backboards in Parish Gym | Completed 11.08.18 |
Repair Pleasant Avenue Wall and Wrought Iron Handrails to Assumption Church | Completed 11.03.18 |
New Statue of Mary Placed Outside the Meeting House at Immaculate Conception on Winter Hill Road | Completed 09.07.18 |
New LED Lights Installed to Illuminate the Properties of Immaculate Conception and Assumption Church | Completed 09.03.18 |
New Roof for the Immaculate Conception Rectory | Completed 08.17.18 |
Install New Signs around the Parking Lots and Property of Immaculate Conception and Assumption of Our Lady | Completed 08.03.18 |
Reset Black Memorial Stones in Slanted Concrete Below the Stations of the Cross in the Prayer Garden | Completed 07.20.18 |
Repair Underground Sprinklers in the Prayer Garden | Completed 07.20.18 |
Repair Right Side of the Waterfall at the St. Francis Grotto of the Prayer Garden | Completed 07.14.18 |
Paint Exterior of Meeting House at Immaculate Conception | Completed 07.12.18 |
Purchase of Earth Excavator for Holy Mount Cemetery | Completed 06.22.18 |
Purchase of 2003 Ford F250 Truck | Completed 05.22.18 |
Replace Handrails to the Lower Church at Immaculate Conception | Completed 05.04.18 |
Replace Old Air Conditioning units at Immaculate Conception Rectory | Completed 03.26.18 |
Renovate Kitchen at Casa Padre Pio (Assumption Rectory) | Completed 03.23.18 |
Paint Interior of Meeting House at Immaculate Conception | Completed 03.17.18 |
Replace Hand-Carved Advent Wreath Forms for both Churches | Completed 12.01.17 |
Re-point and Replace Concrete Staircase at Immaculate Conception Church | Completed 11.26.17 |
Replace Oil Tanks at Assumption Rectory | Completed 11.05.17 |
Acquire and Bless new Statue of St. Pio of Pietrelcina (Padre Pio) | Completed 09.23.17 |
Refurbishment of Stained Glass Windows in the Sacristy of Immaculate Conception Church | Completed 09.07.17 |
Refurbishment and Restoration of the Fatima Statues at Assumption | Completed 08.28.17 |
Convert to LED Lighting in the Lower Church with addition of remote switches | Completed 08.24.17 |
Surveillance System for Immaculate Conception Church: cameras, monitors, Wi-Fi feed | Completed 08.24.17 |
Install Vinyl Siding at the Immaculate Conception Rectory | Completed 08.18.17 |
Repair the Waterfall at the St. Francis Grotto of the Prayer Garden | Completed 08.15.17 |
Refurbish Assumption Rectory 2nd Floor Rooms and Bedrooms | Completed 08.10.17 |
Pour Concrete into Wall Separating at Immaculate Conception Church | Completed 08.05.17 |
Repair Concrete and Add Support to the Lower Wall of Immaculate Conception Church | Completed 08.04.17 |
Acquire New Statue of St. Pio of Pietrelcina for Assumption Church | Completed 08.04.17 |
Repair Statue of Our Lady, Originally at the Convent, but Now in a Garden at the School | Completed 08.04.17 |
Re-pave Walkway to the Back of the Rectory | Completed 08.04.17 |
Re-set and Seal the Blue Stone on the Portico of Immaculate Conception Church (Winter Hill) | Completed 08.03.17 |
Seal and Re-line the Parking Lots at Assumption Church | Completed 07.31.17 |
Re-set and Re-point the Marble Steps to the Lower Church |
Completed 07.31.17 |
Replace Windows in the Meeting House | Completed 06.25.17 |
Replace Frayed Carpeting in the Rectory | Completed 06.02.17 |
Install Air Conditioning System in Parish Gym | Completed 06.01.17 |
Replace Air Conditioning System at Immaculate Conception Church | Completed 05.28.17 |
Repair stairwells to the Lower Church at Immaculate Conception | Completed 05.28.17 |
New Sanctuary Appointments at Immaculate Conception (Candlesticks, Processional Cross, Altar Cross) | Completed 04.15.17 |
Refurbish the Outdoor Softball Field | Completed 04.11.17 |
Install New Boiler for the Immaculate Conception Regional School | Completed 04.11.17 |
Renovate Bathroom of Immaculate Conception Church | Completed 01.18.17 |
Upgrade Sound System at Assumption Church | Completed 12.21.16 |
Replace Windows in the Rectory Garage | Completed 12.09.16 |
Install St. Killian Votive Candle Racks in the Two Churches | Completed 11.23.16 |
New Tile Floor at the Entrance into Immaculate Conception Church | Completed 11.21.16 |
Two New Signs for the Entrances at Assumption Church and Repair the Prayer Garden sign | Completed 10.12.16 |
Replace Outdoor Bulletin Board at Assumption Church | Completed 10.12.16 |
Renovate Fr. Fata Hall (upstairs) | Completed 09.14.16 |
Repair and Paint Statue of Our Lady at Entrance to Assumption | Completed 08.20.16 |
Convert to Energy-Saving LED Lights in the Gym | Completed 08.12.16 |
Repair and Paint Chimney at Fr. Fata Hall | Completed 07.23.16 |
Convert to Energy-Saving LED Lights at Assumption | Completed 05.13.16 |
Refurbish Assumption Rectory 3rd Floor Bedrooms and Bathroom | Completed 05.09.16 |
Convert to Energy-Saving LED Lights at Immaculate Conception | Completed 04.29.16 |
Replace Windows in the Rectory | Completed 04.11.16 |
Update Three Signs at the Entrances to Immaculate Conception | Completed 03.31.16 |
Upgrade Sound System in Immaculate Conception Church | Completed 03.11.16 |